Report on the construction of the RYBALSKY residential neighbourhood

  • calender 01.12.2017

The construction of the RYBALSKY residential neighbourhood is actively continuing! You can find out about the progress and performance of the works by reading the report.

Turn 1

  • Monolithic frame works have been completely executed in sections II, III, IV and V.
  • Monolithic frame works in the remaining sections are at the completion stage.
  • Masonry of external and internal walls is carried out. Section III is actually completed, section II is at the completion stage.
  • Installation of stair flights in sections II, III, IV and V has been completed.
  • The facade works on section III are continuing.
  • The landscaping near sections II, III, IV from the side of the boulevard have been completed.
  • The project of the internal court yard is developed.

Section I

  • Monolithic frame works are at the completion stage: 9 floors are actually built, 10th floor is being completed.
  • Masonry of external and internal walls on the 1st and 2nd floors is being completed. Installation of stair flights has been completed.

Section II

  • Monolithic frame works have been completely executed on 10 floors.
  • Brickwork is at the stage of completion.
  • Installation of stair flights has been completed.
  • Installation of windows on the 1st floor and work on the facade cladding at the level of the 1st floor have began.

Section III

  • Monolithic frame works have been completely executed on 10 floors.
  • Masonry of external and internal walls has been completed, and the installation of stair flights has also been completed.
  • The facade works are continuing up to the 6th floor.
  • Installation of windows on the 1st floor has been completed, works on the 2-6th floors are continuing. A metal fence has been installed on the loggias of the 7th floor.

Section IV

  • Monolithic frame works have been completely executed on 10 floors.
  • Brickwork is being carried out on the 3rd, 4th and 5th floors.
  • Installation of stair flights has been completed.
  • Installation of windows on the 1st floor and work on the facade cladding at the level of the 1st floor have began.

Section V

  • Monolithic frame works have been completely executed on 10 floors.
  • Brickwork is being carried out on the 1st floor.
  • Installation of stair flights has been completed.

Section VI

  • Monolithic frame works have been carried out on 7 floors, the 8th floor is at the completion stage, works on the 9th floor have began.
  • Brickwork is being carried out on the 1st floor.
  • Preparatory work is underway to install stair flights.

Turn 2

  • Monolithic frame works are fully completed in sections I, V, VI. Monolithic frame works are continuing in sections II and III, the works in section IV are at the completion stage.
  • Masonry of external and internal walls has been completed in sections I, V and VI. The facade works are continuing in section VI.
  • The landscaping near the I, V, VI sections from the side of the boulevard has been completed.

Section I

  • Monolithic frame works are fully completed on 10 floors.
  • The brickwork is completed by 10%.
  • The facade works at the level of the 1st floor are at the stage of completion. The installation of windows on the 1st floor is continuing.

Section II

  • Monolithic frame works are actually carried out on 5 floors, the works on the 6th floor are continuing.

Section III

  • Monolithic frame works are 30% completed — 3 floors are actually constructed.

Section IV

  • Monolithic frame works are actually carried out on 7 floors, the works on the 8th floor are continuing.

Section V

  • Monolithic frame works are fully completed on 10 floors.
  • The brickworks are completed on 4 floors, the works on the 5th and 7th floors are continuing, the works on the 6th floor are at the completion stage.
  • The facade works at the level of the 1st floor are at the stage of completion. The installation of windows on the 1st floor has been completed.

Section VI

  • Monolithic frame works on the 9th floor are completed by 50%.
  • The brickwork is completed by 49%.
  • The facade works at the level of the 1st floor are at the stage of completion. The installation of windows on the 1st floor has been completed, the works on the 2nd, 3rd and 4th floors are continuing.

Turn 4

  • The work on the development of a foundation pit for construction is continuing.