State of work

Building 3

1 section:

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Window installation: the work is done by 98%.

Installation of yard windows (2-9 floors): the work is done on 99%.

Roof: work is completed.

Tightening: Work is complete.

Inner decoration: plastering works are executed on 100%, finishing of the finish layer of decorations is carried out (84%), laying of a tile on a floor (90%) in places of general use.

Installation of an apartment door: work is completed.

External networks: external networks continue to be built 86% completed.


Section 2:

Window installation: the work is done by 98%.

Installation of the yard windows (2-9 floor): the work is done on 99%.

Facade works: the work is done on 97%.

Roof: work is completed.

Installation of an apartment door: work is completed.

Tightening: Work is complete.

Interior decoration: plastering works are completed, finishing of the finish layer of decoration and laying of the tile on the floor in public places has been completed.

Internal networks: work performed 95%.


Section 3:

Installation of yard windows (2-9 floors): the work is done on 99%.

Facade: work is completed.

The facade of the courtyard: the work is done on 99%.

Interior decoration: work is finished.

Roof: work is completed.

Tightening: Work is complete.

Installation of doors: apartment doors are mounted.

Elevators: 2 elevators are completed.

Internal networks: 99% work done.


Section 4:

Facade: works completed by 97%.

Tightening: Work is complete.

Elevators: two lifts were installed.

Installation of windows: all floors are finished.

Installation of apartment doors: work is completed.

Interior decoration: finished plastering works, finishing of finishing finish of decorations (99%), laying of a tile on a floor in public places is carried out.

External networks: 98% work performed.


Section 5:

Internal networks (electricity, drainage and sewerage, heating and ventilation): work is completed.

Roof: work is completed.

Tightening: Work is complete.

Window installation: the work is done by 98%.

Installation of yard windows (2-9 floors): the work is done on 99%.

Installation of apartment doors: work is completed.

Interior decoration: finished plastering, finishing of the finishing layer of decoration is done by 76%, laying of the tile on the floor in public places - by 94%.

Facade: The work is done on 49%.

The facade of the courtyard: the work is done by 80%.

External networks: 96% work done.


Section 6:

Facade: The work is done by 63%.

The facade of the courtyard: the work is done by 68%.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work is completed.

Roof: work is completed.

Tightening: Work is complete.

Installation of yard windows (2-9 floors): the work is done on 99%.

Window installation: the work is done by 98%.

Installation of apartment doors: work is completed.

Interior decoration: plastering works are executed on 100%, the finishing of the finish layer of decorations is continuing (78%), the laying of tiles on the floor (92%) is in public places.


Parking:

The installation of the roofing layer of the parking (waterproofing layer) is completed. The basic complex of works with accomplishment made 43%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 93%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 93%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 93%

Accomplishment

Facade

Section 1
Windows - 98%
Facade - 55%
Section 2
Windows - 99%
Facade - 99%
Section 3
Windows - 100%
Facade - 99%
Section 4
Windows - 100%
Facade - 99%
Section 5
Windows - 99%
Facade - 48%
Section 6
Windows - 98%
Facade - 63%

Communications

Section 1
Inside - 82%
Outside - 86%
Section 2
Inside - 98%
Outside - 96%
Section 3
Inside - 98%
Outside - 100%
Section 4
Inside - 98%
Outside - 99%
Section 5
Inside - 84%
Outside - 99%
Section 6
Inside - 87%
Outside - 86%

Building 5

1 section

The work on laying parapoles ends. Brick masonry from 7th to 9th floors is underway. Stair march installation is ongoing.


section 2

The work on laying parapoles ends. Brick masonry from 5th to 9th floors is underway. Stair march installation is ongoing.


Section 3

Brick masonry from the 5th to the 9th floors is underway. Stair march installation is ongoing.


Section 4 (Center for Child Development)

Foundation: the foundation of the basement is completed. Work is being carried out on placing the vertical elements of the 1st floor.


Parking

Foundation: the foundation of the foundation is completed, work on the arrangement of vertical elements of the basement floor is performed.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 98%
Brickwork - 90%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 95%
Brickwork - 70%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 98%
Brickwork - 70%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 0%
Facade - 0%
Section 3
Windows - 0%
Facade - 0%
Section 4
Windows - 0%
Facade - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%

Building 9

1 section:

Facade: the work is done on 96%.

Facade of the courtyard: the work is done 100%.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Installation of windows (2-9 floors): the work is done by 98%.

Installation of yard windows (2-9 floors): the work is done on 99%.

Tightening: Work is complete.

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering works are executed on 100%, drawing of finishing decoration layer (98%), the laying of a tile on a floor in public places is completed.

External Networks: External Networking Work Started - 44% Readiness.

Roof: work is completed.


Section 2:

Facade: the work is done by 40%.

Garden facade: the work is done by 99%.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work is completed.

Tightening: Made 100%.

Installation of windows (2-9 floors): works executed on 94%.

Installation of yard windows (2-9 floors): the work is done on 99%.

Roofing: the membrane stays in place, the total work done is 48%.

Installation of apartment doors: the work is done on 100%.

Internal trim: plastering works are executed on 100%, the finishing of the finish layer of decorations has begun (80%), the laying of a tile on the floor (92%) has been started in public places.


Section 3:

Facade: the work is done by 54%.

Garden facade: the work is done by 99%.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work is completed.

Tightening: Work is complete.

Installation of windows (2-9 floors): works executed on 93%.

Installation of yard windows (2-9 floors): works executed on 99%.

Interior decoration: plastering works are executed on 100%, drawing of a finishing layer of decoration (67%), laying of a tile on a floor (82%) in places of general use.

Installation of apartment doors: the work is done 100%.


Section 4:

Facade: The work is done by 26%.

The facade of the courtyard: the work is done by 96%.

Brickwork: Work is complete.

External networks: External networks have been started the work is done by 83%.

Installation of yard windows (2-9 floors): the work is done on 99%.

Installation of windows (2-9 floors): the work is done on 81%.

Tightening: Work is complete.

Interior decoration: plastering works are executed on 100%, finishing of finishing decoration (62%), laying of a tile on a floor (80%) in places of general use.

Installation of apartment doors: works are executed on 100%.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.


Section 5:

Facade: the work is done by 99%.

Facade of the courtyard: the work is done 100%.

Installation of windows (2-9 floors): work performed on 99%

Installation of yard windows (2-9 floors): the work is done on 99%.

External networks: external networks continue to be built the work is done at 95%.

Tightening: Completed.

Roof: work is completed.

Apartment door installation: completed by 100%.

Interior decoration: finished plastering works, finishing of finishing decoration and laying of tiles on the floor in public places.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.


Section 6:

Facade: the work is done by 99%.

Facade of the courtyard: the work is done 100%.

Installation of windows (2-9 floors): work is completed.

Installation of yard windows (2-9 floors): the work is done on 99%.

Tightening: Made 100%.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Facade works: finished work on facade facing from 2 to 9 floors of aluminum composite panels.

Installation of apartment doors: the work is done 100%.

Interior decoration: finished plastering works, finishing of finishing decoration and laying of tiles on the floor in public places.

Roof: work is completed.


Parking:

The installation of the roofing layer of the parking (waterproofing layer) is completed. The main complex of works on improvement was made by 82%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 93%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 87%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 86%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%

Accomplishment

Facade

Section 1
Windows - 98%
Inside - 95%
Section 2
Windows - 94%
Inside - 40%
Section 3
Windows - 94%
Inside - 54%
Section 4
Windows - 80%
Inside - 24%
Section 5
Windows - 98%
Inside - 99%
Section 6
Windows - 100%
Inside - 99%

Communications

Section 1
Inside - 82%
Outside - 62%
Section 2
Inside - 82%
Outside - 36%
Section 3
Inside - 83%
Outside - 0%
Section 4
Inside - 82%
Outside - 99%
Section 5
Inside - 87%
Outside - 99%
Section 6
Inside - 86%
Outside - 99%

Progress of construction

15 July 2019

05 July 2019

27 June 2019

24 June 2019

14 June 2019

07 June 2019

29 May 2019

23 May 2019

17 May 2019

10 May 2019

04 May 2019

26 April 2019

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016