Building 3

Section 1:

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Window installation: The work is done at 86%.

Installation of yard windows (2-9 floors): the work is done on 98%.

Roof: the laying of the membrane layer has been completed, the total works completed by 72%.

Tightening: Work is complete.

Inner fittings: plastering works are executed on 100%, the finishing of the finish layer of decorations is carried out (55%), laying of a tile on a floor (85%) in places of general use.

Installation of an apartment door: work is completed.


Section 2:

Installation of windows: the work is done by 95%.

Installation of the yard windows (2-9 floor): the work is done on 99%.

Facade work: facing from aluminum composite panels and fiber cement board made 98%. Between 7 and 9 floors of the cladding are completed.

Roof: work is completed.

Installation of an apartment door: work is completed.

Tightening: Work is complete.

Interior fittings: plastering works are completed, finishing of the finish layer of decorations is continuing (90%), the laying of the tile on the floor is completed in public places.

Extranets: work on the laying of external networks has begun, 36% completed.


Section 3:

Installation of yard windows (2-9 floors): the work is done on 99%.

Facade work: facing from aluminum composite panels and installation of HPL panels made by 99%. Between 7 and 9 floors of the cladding are completed.

Interior decoration: work is finished.

Facade of the courtyard: the installation of the heater has been completed, the spackling (97%) and decorative layer finish are completed.

Roof: work is completed.

Tightening: Work is complete.

Installation of doors: apartment doors are mounted.

Elevators: 2 elevators are completed.

Extranets: work on the laying of external networks has begun, 85% completed.


Section 4:

Facade work: facing from aluminum composite panels and fiber cement board is made on 97%. Between 7 and 9 floors of the cladding are completed.

Tightening: Work is complete.

Elevators: two lifts were installed.

Installation of windows: all floors are finished.

Installation of apartment doors: work is completed.

Inner fittings: plastering works are completed, finishing of finishing finishes is carried out (90%), laying of a tile on a floor in public places is carried out.

Extranets: 88% of the work was done on laying out external networks.


Section 5:

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Roof: the laying of the membrane layer has been completed, the total works completed by 86%.

Tightening: Work is complete.

Installing windows: the work is done by 54%.

Installation of yard windows (2-9 floors): the work is done on 98%.

Installation of apartment doors: the work is done on 98%.

Inner fittings: plastering works are executed on 100%, application of finishing layer of decorations (20%), laying of tiles on a floor (45%) in places of general use.

External networks: the work on the laying of external networks has begun, 76% have been completed.

Facade works: mounting of brackets under the ACP system (aluminum composite panels) in volume is 19%.


Section 6:

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Roof: the laying of the membrane layer has been completed, the total works completed by 75%.

Tightening: Work is complete.

Installation of yard windows (2-9 floors): the work is done on 99%.

Window installation: the work is done by 93%.

Installation of apartment doors: the work is done on 98%.

Interior decoration: plastering works are executed on 100%, finishing of the finish layer of decorations is carried out (48%), laying of a tile on a floor (70%) in places of general use.


Parking:

An arrangement of the roofing layer of the parking (corner-forming bottom layer) is carried out. The basic complex of works is executed on 15%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 80%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 65%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 77%

Accomplishment

Facade

Section 1
Windows - 88%
Facade - 37%
Section 2
Windows - 99%
Facade - 87%
Section 3
Windows - 99%
Facade - 99%
Section 4
Windows - 99%
Facade - 87%
Section 5
Windows - 99%
Facade - 24%
Section 6
Windows - 92%
Facade - 34%

Communications

Section 1
Inside - 82%
Outside - 48%
Section 2
Inside - 97%
Outside - 96%
Section 3
Inside - 91%
Outside - 99%
Section 4
Inside - 90%
Outside - 99%
Section 5
Inside - 75%
Outside - 99%
Section 6
Inside - 75%
Outside - 0%

Building 5

Section 1:

Vertical elements: work on the 7th floor has been completed, the placement of the vertical elements of the 8th floor continues, the work is done on 12%.


Section 2:

Vertical elements: work on the 8th floor has been completed.


Section 3:

Vertical elements: the installation of vertical elements of the 5th floor is completed, the installation of vertical elements of the 6th floor continues, the work is done on 33%.


Section 4 (Center for Child Development):

Foundation: foundation foundation (901 m³). Starting up of vertical elements - readiness of 21%


Parking:

Foundation: foundation (261 m³).

General construction works

Section 1
Works against 0,000 - 100%
Frame - 18%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 19%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 16%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 35%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 0%
Facade - 0%
Section 3
Windows - 0%
Facade - 0%
Section 4
Windows - 0%
Facade - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%

Building 9

Section 1:

Facade works: the installation of brackets, frame and heater from 2 to 6 floors is completed, clinker installation work is continuing (80%). Mounting brackets (98%) continues from 7th to 9th floors. Work has begun on the arrangement of facades on balconies and loggias (arrangement of wet facades, performed 29%).

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Installation of windows (2-9 floors): the work is done on 95%.

Installation of the yard windows (2-9 floors): the work is done by 96%.

Brickwork: Work is complete.

Tightening: Work is complete.

Elevators: preparation of elevator shafts for the installation of 2 elevators (95%).

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering works are executed on 100%, drawing of finishing decoration layer (91%), the laying of a tile on a floor in public places is completed.

External Networks: External Networking Work Started - 36% Readiness.


Section 2:

Brickwork: the main volume of work is completed, the engineering niche bookmark continues.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Tightening: Made 100%.

Installation of yard windows (2-9 floors): the work is done on 93%.

Roofing: the membrane is stacked, the total work done is 40%.

Installation of apartment doors: the work is done on 100%.

Internal trim: plastering works are executed on 100%, the finishing of the finish layer of decoration (60%) has begun, the laying of a tile on the floor (75%) has been started in public places.


Section 3:

Brickwork: the main volume of work is completed, the engineering niche bookmark continues.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Internal networks (power supply): work is completed.

Tightening: from 2 to 10 floors completed by 100%.

Roofing: the laying of the insulating layer and the layer that forms the slope of the roof is completed, the membrane has been put into operation, the overall complex of works has been completed by 28%.

Installation of yard windows (2-9 floors): works executed on 96%.

Inner fittings: plastering works are executed on 100%, application of finishing layer of decorations (45%), laying of tiles on a floor (70%) in places of general use.

Installation of apartment doors: the work is done 100%.


Section 4:

Bricklaying: works on the 1st floor (52%) are carried out, the laying of basements and premises of engineering systems (15%) is carried out. On the 9-10 floors there is a laying of internal walls and partitions (65%).

External networks: External networks have been started The work is done at 68%.

Installation of yard windows (2-9 floors): the work is done on 98%.

Installation of windows (2-9 floors): the work is done on 49%.

Tightening: Work is complete.

Roof: the laying of the insulation layer and the layer that forms the slope of the roof is completed, the laying of the membrane has begun, the total works completed by 29%.

Interior decoration: plastering works are executed on 100%, drawing of the finishing layer of decorations (40%), laying of a tile on a floor (65%) in places of general use.

Installation of apartment doors: works are executed on 100%.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.


Section 5:

Facade work: the installation of brackets, frame and heater from the 2nd to the 6th floor is completed, finishing works for the installation of clinker tiles (90%) are underway. Works on the installation of brackets (92%) are ongoing from 7 to 9 floors.

Installation of windows (2-9 floors): work performed on 98%

Installation of yard windows (2-9 floors): the work is done on 95%.

External networks: external networks continue to be built the work is done by 90%.

Tightening: Completed.

Roof: work is completed.

Apartment door installation: completed by 100%.

Interior decoration: plastering works are executed on 100%, drawing of a finishing layer of decoration (91%), the laying of a tile on a floor in public places is completed.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.


Section 6:

Installation of windows (2-9 floors): work performed on 99%

Installation of yard windows (2-9 floors): work performed on 98%

Tightening: Made 100%.

Internal networks (drainage and sewerage, heating and ventilation): work is completed.

Facade works: finished work on facade facing from 2 to 9 floors of aluminum composite panels.

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering works are executed on 100%, drawing of a finishing layer of decoration (91%), the laying of a tile on a floor in public places is completed.

Roof: work is completed.


Parking:

The installation of the roofing layer of the parking is ongoing (the arrangement of the corner-forming bottom concrete layer and the membrane is completed). The basic complex of works is executed on 35%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 78%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 73%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 72%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%

Accomplishment

Facade

Section 1
Windows - 98%
Inside - 90%
Section 2
Windows - 17%
Inside - 8%
Section 3
Windows - 25%
Inside - 14%
Section 4
Windows - 49%
Inside - 0%
Section 5
Windows - 98%
Inside - 96%
Section 6
Windows - 100%
Inside - 99%

Communications

Section 1
Inside - 75%
Outside - 44%
Section 2
Inside - 75%
Outside - 36%
Section 3
Inside - 75%
Outside - 0%
Section 4
Inside - 75%
Outside - 72%
Section 5
Inside - 75%
Outside - 96%
Section 6
Inside - 77%
Outside - 99%

Progress of construction

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016