Internal networks (drainage and sewerage, heating and ventilation): work completed.
Internal networks (power supply): Completed.
Window installation: complete.
Installation of patio windows (2-9 floors): work completed.
Door installation: work completed.
Roof: Completed.
Ties: Work complete.
Interior decoration: all work is done (completion of the finishing layer of finishes and laying tiles on the floor in public places).
Facade: The facade has been completed.
Yard facade: work completed.
Landscaping: 96% completed.
Windows Installation: Completed.
Installation of patio windows (2-9 floors): work completed.
Facade: The facade is finished.
Roof: Completed.
Installation of apartment doors: work completed.
Ties: Work complete.
Interior decoration: plastering works are completed, the finishing layer is finished and the tiles are laid on the floor in public places.
Internal Networks: Completed.
Landscaping: 96% completed.
Installation of patio windows (2-9 floors): work completed.
Facade: Finished.
Yard facade: finishing done.
Interior decoration: work completed.
Roof: Completed.
Ties: Work complete.
Door installation: apartment door mounted.
Elevators: mounted.
Internal networks: 100% completed.
Landscaping: 100% completed.
Facade: Completed.
Ties: flooded.
Elevators: 2 elevators installed.
Installation of windows: completed on all floors.
Installation of apartment doors: work completed.
Interior decoration: plastering works are completed, the finishing layer is finished, tiles are laid on the floor in public places.
Internal Networks: Completed.
Landscaping: 96% completed.
Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.
Roof: Completed.
Ties: Work complete.
Window installation: 100% completed.
Installation of patio windows (2-9 floors): the work is done 100%.
Installation of apartment doors: work completed.
Interior decoration: work completed.
Facade: 100% completed.
Yard facade: 100% completed.
Landscaping: 96% completed.
Facade: 97% completed. Installation of facade protections continues.
Yard facade: work completed.
Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.
Roof: Completed.
Ties: Work complete.
Installation of patio windows (2-9 floors): the work is done 100%.
Window installation: 100% completed.
Installation of apartment doors: work completed.
Interior decoration: work completed.
Landscaping: 96% completed.
Work is underway to install the floor at -1 level (readiness - 85%). Interior finishing works (65%) and laying of a terrace board (50%) are carried out. The main set of landscaping works is completed by 65%.
The grille of section № 1 is filled in. In section № 3 installation of vertical elements of the 2nd floor is carried out. Installation of the floor slab of the 6th floor in section № 4 has been completed. Installation of the facade exhibitor. In section № 6, the slab is poured on the 10th floor, and masonry works are carried out on the 9th floor.
Installation of a sheet pile fence of a pit is carried out.
Facade: 100% completed.
Yard facade: 100% completed.
Internal networks (drainage and sewerage, heating and ventilation): work completed.
Installation of windows (2-9 floors): work completed.
Installation of patio windows (2-9 floors): work completed.
Ties: Work complete.
Installation of apartment doors: the work is done 100%.
Interior decoration: work completed.
Roof: Completed.
Landscaping: 85% completed.
Facade: 95% completed.
Yard facade: 100% work done.
Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.
Ties: 100% complete.
Installation of windows: all work is completed.
Installation of apartment doors: the work is 100% completed.
Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.
Landscaping: 50% completed.
Facade: 100% completed.
Yard facade: 100% completed.
Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.
Ties: Work complete.
Installation of windows (2-9 floors): work completed.
Installation of patio windows (2-9 floors): work completed.
Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.
Installation of apartment doors: the work is done 100%.
Facade: 94% completed.
Yard facade: work completed.
Installation of patio windows (2-9 floors): installation is completed.
Installation of windows (2-9 floors): installation is complete.
Ties: Work complete.
Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.
Installation of apartment doors: the work is done 100%.
Landscaping: 90% completed.
Facade: 100% completed.
Yard facade: 100% completed.
Installation of windows (2-9 floors): installation is complete.
Installation of patio windows (2-9 floors): installation is complete.
Checkboxes: Complete.
Roof: Completed.
Installation of apartment doors: 100% completed.
Interior decoration: plastering, finishing and tiling on public floors have been completed.
Internal networks (drainage and sewerage, heating and ventilation): work completed.
Facade: 100% completed.
Yard facade: 100% completed.
Installation of windows (2-9 floors): installation is complete.
Installation of patio windows (2-9 floors): installation is complete.
Ties: 100% complete.
Internal networks (drainage and sewerage, heating and ventilation): work completed.
Installation of apartment doors: the work is done 100%.
Interior decoration: plastering, finishing and tiling on public floors have been completed.
Roof: Completed.
The main set of landscaping works is completed by 95%. Work on the installation of the floor at 1 level (90%) and -1 level (45%) continues. Finishing works are performed at 1 level (65%) and -1 level (20%). Apply markup.
The grille of section № 1 is filled in. In section № 3 installation of vertical elements of the 2nd floor is carried out. Installation of the floor slab of the 6th floor in sections № 4 and 10th floor in sections №5 and №6 has been completed.
12 January 2021
30 December 2020
23 December 2020
16 December 2020
10 December 2020
03 December 2020
27 October 2020
20 October 2020
11 October 2020
10 October 2020
03 October 2020
27 October 2020
15 October 2020
07 October 2020
01 October 2020
23 September 2020
16 September 2020
10 September 2020
03 September 2020
27 August 2020
19 August 2020
14 August 2020
03 August 2020
23 July 2020
14 July 2020
03 July 2020
25 June 2020
17 June 2020
11 June 2020
03 June 2020
27 May 2020
21 May 2020
12 May 2020
06 May 2020
28 April 2020
21 April 2020
14 April 2020
06 April 2020
30 March 2020
25 March 2020
16 March 2020
10 March 2020
05 March 2020
20 February 2020
10 February 2020
03 February 2020
27 January 2020
17 January 2020
11 January 2020
08 January 2020
21 December 2019
09 December 2019
09 December 2019
29 November 2019
22 November 2019
18 November 2019
11 November 2019
28 October 2019
21 October 2019
15 October 2019
07 October 2019
30 September 2019
17 September 2019
12 September 2019
02 September 2019
27 August 2019
19 August 2019
12 August 2019
02 August 2019
26 July 2019
22 July 2019
15 July 2019
05 July 2019
27 June 2019
24 June 2019
14 June 2019
07 June 2019
29 May 2019
23 May 2019
17 May 2019
10 May 2019
04 May 2019
26 April 2019
19 April 2019
22 March 2019
13 March 2019
07 March 2019
27 февраля 2019
21 February 2019
14 February 2019
07 February 2019
04 February 2019
21 January 2019
11 January 2019
08 January 2019
28 December 2018
18 December 2018
20 November 2018
09 November 2018
02 November 2018
26 October 2018
19 October 2018
08 October 2018
26 September 2018
02 October 2018
26 September 2018
18 September 2018
12 September 2018
03 September 2018
27 August 2018
20 August 2018
16 August 2018
7 August 2018
30 July 2018
23 July 2018
16 July 2018
9 July 2018
2 July 2018
23 June 2018
18 June 2018
12 June 2018
May 29, 2018
May 22, 2018
May 15, 2018
May 2, 2018
April 16, 2018
April 10, 2018
March 28, 2018
March 19, 2018
March 5, 2018
February 28, 2018
February 21, 2018
February 13, 2018
February 8, 2018
January 24, 2018
January 15, 2018
January 09, 2018
December 26, 2017
December 20, 2017
December 12, 2017
November 30, 2017
November 28, 2017
November 21, 2017
November 11, 2017
November 02, 2017
October 25, 2017
October 11, 2017
October 05, 2017
September 22, 2017
September 18, 2017
September 11, 2017
September 4, 2017
August 22, 2017
August 10, 2017
June 16, 2017
June 12, 2017
June 2, 2017
May 23, 2017
May 12, 2017
March 31, 2017
February 20, 2017
February 9, 2017
January 30, 2017
January 14, 2017
December 20, 2016
December 8, 2016
November 14, 2016