State of work

Building 3

1 section:

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Internal Networks (Power Supply): Done.

Window Mounting: 98% completed.

Installation of yard windows (2-9 floors): 99% work done.

Roofing: Work is complete.

Checkboxes: Completed.

Interior equipment: 100% plastering works, finishing finishes (94%), tile flooring (99%) in public areas.

Facade: 72% completed.

Courtyard: 99% completed.

Improvement: 22% completed.


Section 2:

Window Mounting: 99% completed.

Installation of yard windows (2-9 floors): 99% work done.

Facade: 97% completed.

Roofing: Work is complete.

Flat Door Installation: Completed.

Checkboxes: Completed.

Interior Finishing: Plastering completed, finishing of finishing and tiling on public floors.

Internal Networks: 99% completed.

Improvement: 45% completed.

Door Installation: Completed.


Section 3:

Installation of yard windows (2-9 floors): 99% work done.

Facade: Completed.

Courtyard: 99% completed.

Interior equipment: work in progress.

Roofing: Work is complete.

Checkboxes: Completed.

Door Installation: Apartment doors are installed.

Elevators: 2 elevators complete.

Internal Networks: 99% completed.

Improvement: 99% completed.


Section 4:

Facade: 97% completed.

Checkboxes: Completed.

Elevators: 2 elevators have been installed.

Window Installation: All floors are complete.

Apartment door installation: work is complete.

Interior Finishing: Finished plastering, finishing finish (99%), tile flooring in public areas.

External Networks: 99% completed.

Improvement: 90% completed.


Section 5:

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Roofing: Work is complete.

Checkboxes: Completed.

Window Mounting: 98% completed.

Installation of yard windows (2-9 floors): 99% work done.

Apartment Door Installation: Completed.

Interior Finish: Plastering completed, 90% finishing coat applied, tile flooring in public areas - 99% complete.

Facade: 88% work done.

Courtyard: 99% completed.

Improvement: 90% completed.


Section 6:

Facade: 83% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Roofing: Work is complete.

Checkboxes: Completed.

Installation of yard windows (2-9 floors): 99% work done.

Window Mounting: 98% completed.

Apartment Door Installation: Completed.

Interior decoration: 100% plastering works, finishing finishes (91%), tile flooring (99%) in public areas.

Improvement: 30% completed.


Parking:

The roofing layer is being arranged and the waterproofing layer is being completed. The main complex of works with improvement was completed by 43%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 97%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 96%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 96%

Accomplishment

Facade

Section 1
Windows - 98%
Facade - 71%
Section 2
Windows - 99%
Facade - 99%
Section 3
Windows - 100%
Facade - 99%
Section 4
Windows - 100%
Facade - 99%
Section 5
Windows - 99%
Facade - 88%
Section 6
Windows - 98%
Facade - 77%

Communications

Section 1
Inside - 82%
Outside - 96%
Section 2
Inside - 99%
Outside - 100%
Section 3
Inside - 99%
Outside - 100%
Section 4
Inside - 99%
Outside - 100%
Section 5
Inside - 87%
Outside - 99%
Section 6
Inside - 89%
Outside - 96%

Building 5

1 section

Roof waterproofing works are in progress.


Section 2

Roof waterproofing works are in progress.


Section 3

Work is done on the arrangement of masonry and railings on the roof.


Section 4 (Child Development Center)

Work is done on the arrangement of masonry and railings on the roof.


Parking

Work is underway to arrange the parapets of the first floor.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 99%
Brickwork - 99%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 97%
Brickwork - 35%
Interior fittings - 0%
Parking
Works against 0,000 - 95%
Frame - 95%
Brickwork - 70%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 0%
Facade - 0%
Section 3
Windows - 0%
Facade - 0%
Section 4
Windows - 0%
Facade - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%

Building 9

1 section:

Facade: The work is 98% complete.

Courtyard: 100% complete.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Window Mounting (2-9 floors): 98% completed.

Installation of yard windows (2-9 floors): 99% work done.

Checkboxes: Completed.

Apartment door installation: 100% complete.

Interior decoration: 100% plastering, finishing finish (98%), tile flooring in public areas.

Roofing: Work is complete.


Section 2:

Facade: 65% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Couplings: 100% complete.

Window Mounting (2-9 floors): 94% work done.

Installation of yard windows (2-9 floors): 99% work done.

Installation of apartment doors: 100% complete.

Interior Finishing: 100% plastering, 90% finishes applied, 94% tile flooring in public areas.


Section 3:

Facade: 72% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Checkboxes: Completed.

Window Mounting (2-9 floors): 93% work done.

Installation of yard windows (2-9 floors): 99% work done.

Interior decoration: 100% plastering, finishing finish (75%), floor tiling (93%) in public areas.

Apartment door installation: 100% complete.


Section 4:

Facade: 36% completed.

Courtyard: 96% completed.

Brickwork: works completed.

External networks: External networks have been laid, 83% of work was done.

Installation of yard windows (2-9 floors): 99% work done.

Installation of windows (2-9 floors): 96% work done.

Checkboxes: Completed.

Interior fittings: 100% plastering, finishing (74%), tile flooring (86%) in public areas.

Apartment door installation: 100% complete.


Section 5:

Facade: The work is 99% complete.

Courtyard: 100% complete.

Window Mounting (2-9 floors): 99% done

Installation of yard windows (2-9 floors): 99% work done.

Couplings: Completed.

Roof: Work is complete.

Apartment door installation: 100% complete.

Interior Finishing: Finish plastering, finishing finishes, and tile flooring in public areas.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.


Section 6:

Facade: The work is 99% complete.

Courtyard: 100% complete.

Installation of windows (2-9 floors): work in progress.

Installation of yard windows (2-9 floors): 99% complete work

Couplings: 100% complete.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Apartment door installation: 100% complete.

Interior Finishing: Finish plastering, finishing finishes, and tile flooring in public areas.

Roofing: Work is complete.


Parking:

The roofing layer is being arranged and the waterproofing layer is being completed. The main complex of works with the accomplishment was performed by 95%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 95%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 91%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 88%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%

Accomplishment

Facade

Section 1
Windows - 98%
Inside - 97%
Section 2
Windows - 95%
Inside - 64%
Section 3
Windows - 94%
Inside - 72%
Section 4
Windows - 95%
Inside - 34%
Section 5
Windows - 98%
Inside - 99%
Section 6
Windows - 100%
Inside - 99%

Communications

Section 1
Inside - 99%
Outside - 62%
Section 2
Inside - 85%
Outside - 36%
Section 3
Inside - 86%
Outside - 0%
Section 4
Inside - 82%
Outside - 99%
Section 5
Inside - 87%
Outside - 99%
Section 6
Inside - 99%
Outside - 100%

Building 11

Work is underway to arrange the pile field. The number of crush piles is 1225 pieces: 109 piles are forgotten in the first section, 167 in the second section, 175 in the third section, 140, 5th, the 170th, 6th sections sections - 281, 7th sections - 160, 8th sections - 61, in the parking lot - 332 piles.

General construction works

Section 1
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 0%
Frame - 9%
Brickwork - 0%
Interior fittings - 0%
Section 5
Works against 0,000 - 0%
Frame - 9%
Brickwork - 0%
Interior fittings - 0%
Section 6
Works against 0,000 - 0%
Frame - 2%
Brickwork - 0%
Interior fittings - 0%
Section 7
Works against 0,000 - 0%
Frame - 9%
Brickwork - 0%
Interior fittings - 0%
Section 8
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Inside - 0%
Section 2
Windows - 0%
Inside - 0%
Section 3
Windows - 0%
Inside - 0%
Section 4
Windows - 0%
Inside - 0%
Section 5
Windows - 0%
Inside - 0%
Section 6
Windows - 0%
Inside - 0%
Section 7
Windows - 0%
Inside - 0%
Section 8
Windows - 0%
Inside - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Section 5
Inside - 0%
Outside - 0%
Section 6
Inside - 0%
Outside - 0%
Section 7
Inside - 0%
Outside - 0%
Section 8
Inside - 0%
Outside - 0%

Progress of construction

18 November 2019

11 November 2019

28 October 2019

21 October 2019

15 October 2019

07 October 2019

30 September 2019

17 September 2019

12 September 2019

02 September 2019

27 August 2019

19 August 2019

12 August 2019

02 August 2019

26 July 2019

22 July 2019

15 July 2019

05 July 2019

27 June 2019

24 June 2019

14 June 2019

07 June 2019

29 May 2019

23 May 2019

17 May 2019

10 May 2019

04 May 2019

26 April 2019

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016