State of work

Building 3

1 section:

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Internal Networks (Power Supply): Done.

Window Mounting: 98% completed.

Installation of yard windows (2-9 floors): 99% complete.

Door Installation: Completed.

Roof: Work is complete.

Checkboxes: Completed.

Interior equipment: 100% plastering works, finishing finishes (98%), tile flooring (99%) in public areas.

Facade: 72% completed.

Courtyard: 99% completed.

Improvement: 96% of work is done.


Section 2:

Window Mounting: 99% done.

Installation of yard windows (2-9 floors): 99% complete.

Facade: 97% completed.

Roof: Work is complete.

Flat Door Installation: Completed.

Checkboxes: Completed.

Interior Finishing: Plastering completed, finishing of finishing and tiling on public floors.

Internal Networks: 99% completed.

Improvement: 96% of work is done.


Section 3:

Installation of yard windows (2-9 floors): 99% complete.

Facade: Completed.

Courtyard: 99% completed.

Interior equipment: work in progress.

Roofing: Finished.

Checkboxes: Completed.

Door Installation: Apartment doors are installed.

Elevators: 2 elevators complete.

Internal Networks: 99% completed.

Improvement: 99% completed.


Section 4:

Facade: 97% completed.

Checkboxes: Completed.

Elevators: 2 elevators have been installed.

Window Installation: All floors are complete.

Apartment Door Installation: Completed.

Interior Finishing: Finished plastering, finishing finish (99%), tile flooring in public areas.

External Networks: 99% completed.

Improvement: 96% of work is done.


Section 5:

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Roof: Work is complete.

Checkboxes: Completed.

Window Mounting: 98% completed.

Installation of yard windows (2-9 floors): 99% complete.

Apartment Door Installation: Completed.

Interior Finishing: Plastering completed, 98% finished finish, 99% tile flooring in public areas.

Facade: 88% completed.

Courtyard: 99% completed.

Improvement: 96% of work is done.


Section 6:

Facade: 83% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Roof: Work is complete.

Checkboxes: Completed.

Installation of yard windows (2-9 floors): 99% complete.

Window Mounting: 98% completed.

Apartment Door Installation: Completed.

Interior equipment: 100% plastering works, finishing finishes (98%), tile flooring (99%) in public areas.

Improvement: 96% of work is done.


Parking:

The installation of the roofing layer of the parking lot is underway, the work on the arrangement of the waterproofing layer is completed. The main complex of works with improvement was accomplished by 43%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 97%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 99%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 97%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 97%

Accomplishment

Facade

Section 1
Windows - 98%
Facade - 71%
Section 2
Windows - 99%
Facade - 99%
Section 3
Windows - 100%
Facade - 99%
Section 4
Windows - 100%
Facade - 99%
Section 5
Windows - 99%
Facade - 88%
Section 6
Windows - 98%
Facade - 82%

Communications

Section 1
Inside - 90%
Outside - 96%
Section 2
Inside - 99%
Outside - 100%
Section 3
Inside - 99%
Outside - 100%
Section 4
Inside - 99%
Outside - 100%
Section 5
Inside - 87%
Outside - 99%
Section 6
Inside - 94%
Outside - 96%

Building 5

1 section

Roof waterproofing and terraces are in the works. Installation of internal networks, installation of windows and translucent enclosures is ongoing.


Section 2

Roof waterproofing and terraces are in the works. Installation of internal networks, installation of windows and translucent enclosures is ongoing.


Section 3

Roof waterproofing work is in progress. Installation of internal networks, installation of windows and translucent enclosures is ongoing.


Section 4 (Child Development Center)

Masonry is in progress.


Parking:

Masonry is in progress.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 95%
Interior fittings - 0%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 95%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 0%
Facade - 0%
Section 3
Windows - 0%
Facade - 0%
Section 4
Windows - 0%
Facade - 0%

Communications

Section 1
Inside - 60%
Outside - 5%
Section 2
Inside - 0%
Outside - 20%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%

Building 9

1 section:

Facade: The work is 98% complete.

Courtyard: 100% complete.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Window Mounting (2-9 floors): 98% completed.

Installation of yard windows (2-9 floors): 99% complete.

Checkboxes: Completed.

Apartment door installation: 100% complete.

Interior equipment: 100% plastering, finishing finish (98%), floor tile in public areas.

Roof: Work is complete.


Section 2:

Facade: 72% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Couplings: 100% complete.

Installation of windows (2-9 floors): 94% work done.

Installation of yard windows (2-9 floors): 99% complete.

Installation of apartment doors: 100% complete.

Interior equipment: 100% plastering work, finishing finish (98%), tile flooring (99%) in public areas.


Section 3:

Facade: 78% completed.

Courtyard: 99% completed.

Internal networks (electricity, water and sewerage, heating and ventilation): work is complete.

Checkboxes: Completed.

Window Mounting (2-9 floors): 93% work done.

Installation of courtyard windows (2-9 floors): 99% completed.

Interior decoration: 100% plastering, finishing (87%), tile flooring (95%) in public areas.

Apartment door installation: 100% complete.


Section 4:

Facade: 49% completed.

Courtyard: 96% completed.

Installation of yard windows (2-9 floors): 99% complete.

Installation of windows (2-9 floors): 96% work done.

Checkboxes: Completed.

Interior fittings: 100% plastering, 92% finishing, tile flooring (94%) in public areas.

Apartment door installation: 100% complete.


Section 5:

Facade: 99% completed.

Courtyard: 100% complete.

Window Mounting (2-9 floors): 99% done

Installation of yard windows (2-9 floors): 99% complete.

Screeds: Completed.

Roof: Work is complete.

Apartment door installation: 100% complete.

Interior Finishing: Finish plastering, finishing finishes and tile flooring in public areas.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.


Section 6:

Facade: 99% completed.

Courtyard: 100% complete.

Installation of windows (2-9 floors): work in progress.

Installation of yard windows (2-9 floors): 99% complete work

Couplings: 100% complete.

Internal networks (drainage and sewerage, heating and ventilation): work is complete.

Apartment door installation: 100% complete.

Interior Finishing: Finish plastering, finishing finishes and tile flooring in public areas.

Roof: Work is complete.


Parking:

The roofing layer of the parking lot is being arranged and the waterproofing layer is being completed. The main complex of works with the accomplishment was performed by 95%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 97%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 93%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 92%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 99%
Interior fittings - 99%

Accomplishment

Facade

Section 1
Windows - 98%
Inside - 97%
Section 2
Windows - 95%
Inside - 72%
Section 3
Windows - 94%
Inside - 78%
Section 4
Windows - 95%
Inside - 48%
Section 5
Windows - 98%
Inside - 99%
Section 6
Windows - 100%
Inside - 99%

Communications

Section 1
Inside - 99%
Outside - 74%
Section 2
Inside - 91%
Outside - 36%
Section 3
Inside - 86%
Outside - 0%
Section 4
Inside - 84%
Outside - 99%
Section 5
Inside - 87%
Outside - 99%
Section 6
Inside - 99%
Outside - 100%

Building 11

Pile field works are being carried out: 109 piles have been neglected in the 1st section, 167 in the 2nd section, 175 in the 3rd section, 140, 5th, 170, 6th sections in the 5th section sections - 281, 7th sections - 160, 8th sections - 61, in the parking lot - 332 piles. The number of piles is 1258 pcs, the number of piles is 337 pcs.

General construction works

Section 1
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 6%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 18%
Brickwork - 0%
Interior fittings - 0%
Section 5
Works against 0,000 - 100%
Frame - 24%
Brickwork - 0%
Interior fittings - 0%
Section 6
Works against 0,000 - 100%
Frame - 24%
Brickwork - 0%
Interior fittings - 0%
Section 7
Works against 0,000 - 100%
Frame - 28%
Brickwork - 0%
Interior fittings - 0%
Section 8
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Inside - 0%
Section 2
Windows - 0%
Inside - 0%
Section 3
Windows - 0%
Inside - 0%
Section 4
Windows - 0%
Inside - 0%
Section 5
Windows - 0%
Inside - 0%
Section 6
Windows - 0%
Inside - 0%
Section 7
Windows - 0%
Inside - 0%
Section 8
Windows - 0%
Inside - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Section 5
Inside - 0%
Outside - 0%
Section 6
Inside - 0%
Outside - 0%
Section 7
Inside - 0%
Outside - 0%
Section 8
Inside - 0%
Outside - 0%

Progress of construction

20 February 2020

10 February 2020

03 February 2020

27 January 2020

17 January 2020

11 January 2020

08 January 2020

21 December 2019

09 December 2019

09 December 2019

29 November 2019

22 November 2019

18 November 2019

11 November 2019

28 October 2019

21 October 2019

15 October 2019

07 October 2019

30 September 2019

17 September 2019

12 September 2019

02 September 2019

27 August 2019

19 August 2019

12 August 2019

02 August 2019

26 July 2019

22 July 2019

15 July 2019

05 July 2019

27 June 2019

24 June 2019

14 June 2019

07 June 2019

29 May 2019

23 May 2019

17 May 2019

10 May 2019

04 May 2019

26 April 2019

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016