Building 3

Section 3:

Internal communications: all risers from 1st to 9th floor are completed.

General construction works

Accomplishment

Facade

Communications

Section 1
Works against 0,000 - 100%
Frame - 98,00%
Brickwork - 46%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 99,30%
Brickwork - 87,00%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 100,00%
Brickwork - 86,50%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 99,10%
Brickwork - 86,40%
Interior fittings - 0%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 43%
Interior fittings - 0%
Section 6
Works against 0,000 - 99%
Frame - 98,00%
Brickwork - 44%
Interior fittings - 0%
Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 2,78%
Facade - 8,56%
Section 3
Windows - 61,11%
Facade - 61,11%
Section 4
Windows - 61,11%
Facade - 28,44%
Section 5
Windows - 49,44%
Facade - 0%
Section 6
Windows - 0%
Facade - 0%
Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 23%
Section 3
Inside - 4,1%
Outside - 23%
Section 4
Inside - 0%
Outside - 23%
Section 5
Inside - 0%
Outside - 0%
Section 6
Inside - 0%
Outside - 0%

Building 9

Section 4:

Monolithic works are completed on the 8th floor.

Masonry works are completed on the 6th floor.


Section 5:

16 window frames from 2nd to 6th floor are mounted.


Section 6:

Masonry works are completed on the 10th floor.

General construction works

Accomplishment

Facade

Communications

Section 1
Works against 0,000 - 100%
Frame - 99,60%
Brickwork - 47,09%
Interior fittings - 0%
Section 2
Works against 0,000 - 99%
Frame - 92%
Brickwork - 17%
Interior fittings - 0%
Section 3
Works against 0,000 - 99,00%
Frame - 41%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 99%
Frame - 75,10%
Brickwork - 26%
Interior fittings - 0%
Section 5
Works against 0,000 - 100%
Frame - 99,80%
Brickwork - 78,64%
Interior fittings - 0%
Section 6
Works against 0,000 - 100%
Frame - 99,60%
Brickwork - 60,45%
Interior fittings - 0%
Section 1
Windows - 2,5%
Inside - 8,5%
Section 2
Windows - 0%
Inside - 0%
Section 3
Windows - 0%
Inside - 0%
Section 4
Windows - 0%
Inside - 0%
Section 5
Windows - 13,7%
Inside - 8,5%
Section 6
Windows - 55,00%
Inside - 49,0%
Section 1
Inside - 0%
Outside - 23%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Section 5
Inside - 0%
Outside - 23%
Section 6
Inside - 0%
Outside - 23%

Progress of construction

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016