Лого Жилого района Рыбальский город Киев
Telephone call

*

*

State of work

Building 3

1 section:

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Internal networks (power supply): work completed.

Installation of windows: work completed.

Installation of yard windows (2-9 floors): work completed.

Installation of doors: work is completed.

Roof: work completed.

Ties: work completed.

Interior decoration: all works have been completed (application of the finishing layer of finishes and laying tiles on the floor in public places has been completed).

Facade: the facade is finished.

Yard facade: work completed.

Landscaping: the work is done by 96%.


2 section:

Installation of windows: work completed.

Installation of yard windows (2-9 floors): work completed.

Facade: the facade is finished.

Roof: work completed.

Installation of apartment doors: work completed.

Ties: work completed.

Interior decoration: plastering works have been completed, the application of the finishing layer of finishes and laying of tiles on the floor in public places has been completed.

Internal networks: work completed.

Landscaping: the work is done by 96%.


3 section:

Installation of yard windows (2-9 floors): work completed.

Facade: finishing done.

The facade is yard: the decoration is done.

Interior decoration: work completed.

Roof: work completed.

Ties: work completed.

Installation of doors: apartment doors are mounted.

Elevators: mounted.

Internal networks: the work is 100% completed.

Landscaping: the work is 100% completed.


4 section:

Facade: work completed.

Ties: flooded.

Elevators: 2 elevators were installed.

Installation of windows: work is completed on all floors.

Installation of apartment doors: work completed.

Interior decoration: plastering works have been completed, the finishing layer of finishes has been applied, tiles have been laid on the floor in public places.

Internal networks: work completed.

Landscaping: the work is done by 96%.


5 section:

Внутрішні мережі (електропостачання, водовідвід та каналізація, опалення та вентиляція): роботи завершено.

Покрівля: роботи завершено.

Стяжки: роботи завершено.

Монтаж вікон: роботи виконано на 100%.

Монтаж дворових вікон (2-9 поверхи): роботи виконано на 100%.

Монтаж квартирних дверей: роботи завершено.

Внутрішнє опорядження: роботи завершено.

Фасад: роботи виконано на 100%.

Фасад дворовий: роботи виконано на 100%.

Благоустрій: роботи виконано на 96%.


6 section:

Facade: the work is done by 97%. Installation of facade protections proceeds.

Yard facade: work completed.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Roof: work completed.

Ties: work completed.

Installation of yard windows (2-9 floors): the work is done 100%.

Installation of windows: the work is done 100%.

Installation of apartment doors: work completed.

Interior decoration: work completed.

Landscaping: the work is done by 96%.


Parking:

Work is underway to install the floor at -1 level (readiness - 85%). Interior finishing works (65%) and laying of a terrace board (50%) are carried out. The main set of landscaping works is completed by 65%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 30%

Accomplishment

Facade

Section 1
Windows - 100%
Facade - 100%
Section 2
Windows - 100%
Facade - 100%
Section 3
Windows - 100%
Facade - 100%
Section 4
Windows - 100%
Facade - 100%
Section 5
Windows - 100%
Facade - 100%
Section 6
Windows - 100%
Facade - 100%

Communications

Section 1
Inside - 100%
Outside - 100%
Section 2
Inside - 100%
Outside - 100%
Section 3
Inside - 100%
Outside - 100%
Section 4
Inside - 100%
Outside - 100%
Section 5
Inside - 100%
Outside - 100%
Section 6
Inside - 100%
Outside - 100%
Parking
Inside - 100%
Outside - 100%

Building 5

1 section

Installation of internal networks, installation of windows and translucent enclosing structures continues. The facade is being finished. Works on internal furnish pass, fill in a coupler (readiness - 90%).


2 section

Installation of internal networks, installation of windows and translucent enclosing structures continues. Works on the arrangement of the facade are underway. Work is underway on the interior, continue to pour screed on the floor (70%).


3 section

Installation of internal networks, installation of windows and translucent enclosing structures continues. Works on the arrangement of the facade and installation of the subsystem are underway. Work on the interior is underway, continue to pour screed on the floor (10%).


Section 4 (Child Development Center)

Installation of translucent enclosing structures is performed.


Parking

Waterproofing works are underway.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 30%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 7%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 0%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 99%
Facade - 80%
Section 2
Windows - 99%
Facade - 70%
Section 3
Windows - 99%
Facade - 35%
Section 4
Windows - 30%
Facade - 0%

Communications

Section 1
Inside - 65%
Outside - 100%
Section 2
Inside - 55%
Outside - 100%
Section 3
Inside - 30%
Outside - 40%
Section 4
Inside - 0%
Outside - 50%
Parking
Outside - 100%

Building 9

1 section

Facade: the work is done by 98%.

The facade is yard: the work is 100% done.

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Installation of windows (2-9 floors): the work is done by 98%.

Installation of yard windows (2-9 floors): the work is done by 99%.

Ties: work completed.

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering works are performed 100%, application of the finishing layer of decoration (98%), laying of tiles on the floor in public places is completed.

Roof: work completed.

Landscaping: work is done by 55%.


Section 2:

Facade: 95% completed.

The facade is yard: the work is done by 99%.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Ties: 100% made.

Installation of windows (2-9 floors): the work is done by 93%.

Installation of yard windows (2-9 floors): the work is done by 99%.

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering works were performed 100%, the finishing layer of finishing was started (98%), laying of tiles on the floor (99%) was started in public places.

Landscaping: work is done by 40%.


Section 3:

Facade: 95% completed.

The facade is yard: the work is done by 99%.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Ties: work completed.

Installation of windows (2-9 floors): the work is done by 93%.

Installation of yard windows (2-9 floors): the work is done by 99%.

Interior decoration: plaster work is done 100%, application of the finishing layer of finishes (87%), laying of tiles on the floor (95%) in public places.

Installation of apartment doors: the work is done 100%.


Section 4:

Facade: 94% completed.

The facade is yard: the work is done by 96%.

Installation of yard windows (2-9 floors): the work is done by 99%.

Installation of windows (2-9 floors): the work is done by 96%.

Ties: work completed.

Interior decoration: plastering works are performed 100%, application of the finishing layer of finishes (92%), laying of tiles on the floor (94%) in public places.

Installation of apartment doors: the work is done 100%.

Landscaping: 90% of the work is done.


Section 5:

Facade: 99% completed.

The facade is yard: the work is 100% done.

Installation of windows (2-9 floors): the work is done by 99%.

Installation of yard windows (2-9 floors): the work is done by 99%.

Ties: completed.

Roof: work completed.

Installation of apartment doors: made 100%.

Interior decoration: completed plastering, application of a finishing layer of finishes and laying tiles on the floor in public places.

Internal networks (drainage and sewerage, heating and ventilation): work completed.


Section 6:

Facade: 99% completed.

The facade is yard: the work is 100% done.

Installation of windows (2-9 floors): work completed.

Installation of yard windows (2-9 floors): the work is done by 99%.

Ties: 100% made.

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Installation of apartment doors: the work is done 100%.

Interior decoration: completed plastering, application of a finishing layer of finishes and laying tiles on the floor in public places.

Roof: work completed.


Parking:

Installation of the roofing layer of the parking lot is underway, work on the installation of the waterproofing layer is completed. The main set of landscaping works has been completed by 95%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100100%
Interior fittings - 100%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 42%

Accomplishment

Facade

Section 1
Windows - 100%
Inside - 100%
Section 2
Windows - 100%
Inside - 95%
Section 3
Windows - 100%
Inside - 100%
Section 4
Windows - 100%
Inside - 95%
Section 5
Windows - 100%
Inside - 100%
Section 6
Windows - 100%
Inside - 100%

Communications

Section 1
Inside - 100%
Outside - 97%
Section 2
Inside - 100%
Outside - 97%
Section 3
Inside - 96%
Outside - 100%
Section 4
Inside - 1006%
Outside - 97%
Section 5
Inside - 100%
Outside - 100%
Section 6
Inside - 100%
Outside - 100%

Building 11

Pile field works are being carried out: 109 piles have been neglected in the 1st section, 167 in the 2nd section, 175 in the 3rd section, 140, 5th, 170, 6th sections in the 5th section sections - 281, 7th sections - 160, 8th sections - 61, in the parking lot - 332 piles. The number of piles is 1258 pcs, the number of piles is 337 pcs.

A tower crane is installed on the house. In section № 4 the arrangement of the horizontal formwork of the 4th floor is performed.

General construction works

Section 1
Works against 0,000 - 66%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 64%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 9%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 30%
Brickwork - 0%
Interior fittings - 0%
Section 5
Works against 0,000 - 100%
Frame - 75%
Brickwork - 15%
Interior fittings - 0%
Section 6
Works against 0,000 - 100%
Frame - 77%
Brickwork - 15%
Interior fittings - 0%
Section 7
Works against 0,000 - 100%
Frame - 80%
Brickwork - 15%
Interior fittings - 0%
Section 8
Works against 0,000 - 100%
Frame - 15%
Brickwork - 0%
Interior fittings - 0%
Parking
Works against 0,000 - 100%
Frame - 50%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Inside - 0%
Section 2
Windows - 0%
Inside - 0%
Section 3
Windows - 0%
Inside - 0%
Section 4
Windows - 0%
Inside - 0%
Section 5
Windows - 0%
Inside - 0%
Section 6
Windows - 0%
Inside - 0%
Section 7
Windows - 0%
Inside - 0%
Section 8
Windows - 0%
Inside - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Section 5
Inside - 0%
Outside - 0%
Section 6
Inside - 0%
Outside - 0%
Section 7
Inside - 0%
Outside - 0%
Section 8
Inside - 0%
Outside - 0%

Progress of construction

27 October 2020

15 October 2020

07 October 2020

01 October 2020

23 September 2020

16 September 2020

10 September 2020

03 September 2020

27 August 2020

19 August 2020

14 August 2020

03 August 2020

23 July 2020

14 July 2020

03 July 2020

25 June 2020

17 June 2020

11 June 2020

03 June 2020

27 May 2020

21 May 2020

12 May 2020

06 May 2020

28 April 2020

21 April 2020

14 April 2020

06 April 2020

30 March 2020

25 March 2020

16 March 2020

10 March 2020

05 March 2020

20 February 2020

10 February 2020

03 February 2020

27 January 2020

17 January 2020

11 January 2020

08 January 2020

21 December 2019

09 December 2019

09 December 2019

29 November 2019

22 November 2019

18 November 2019

11 November 2019

28 October 2019

21 October 2019

15 October 2019

07 October 2019

30 September 2019

17 September 2019

12 September 2019

02 September 2019

27 August 2019

19 August 2019

12 August 2019

02 August 2019

26 July 2019

22 July 2019

15 July 2019

05 July 2019

27 June 2019

24 June 2019

14 June 2019

07 June 2019

29 May 2019

23 May 2019

17 May 2019

10 May 2019

04 May 2019

26 April 2019

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016