State of work

Building 3

1 section:

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Internal networks (power supply): Completed.

Window installation: complete.

Installation of patio windows (2-9 floors): work completed.

Door installation: work completed.

Roof: Completed.

Ties: Work complete.

Interior decoration: all work is done (completion of the finishing layer of finishes and laying tiles on the floor in public places).

Facade: The facade has been completed.

Yard facade: work completed.

Landscaping: 96% completed.


Section 2:

Windows Installation: Completed.

Installation of patio windows (2-9 floors): work completed.

Facade: The facade is finished.

Roof: Completed.

Installation of apartment doors: work completed.

Ties: Work complete.

Interior decoration: plastering works are completed, the finishing layer is finished and the tiles are laid on the floor in public places.

Internal Networks: Completed.

Landscaping: 96% completed.


Section 3:

Installation of patio windows (2-9 floors): work completed.

Facade: Finished.

Yard facade: finishing done.

Interior decoration: work completed.

Roof: Completed.

Ties: Work complete.

Door installation: apartment door mounted.

Elevators: mounted.

Internal networks: 100% completed.

Landscaping: 100% completed.


Section 4:

Facade: Completed.

Ties: flooded.

Elevators: 2 elevators installed.

Installation of windows: completed on all floors.

Installation of apartment doors: work completed.

Interior decoration: plastering works are completed, the finishing layer is finished, tiles are laid on the floor in public places.

Internal Networks: Completed.

Landscaping: 96% completed.


Section 5:

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Roof: Completed.

Ties: Work complete.

Window installation: 100% completed.

Installation of patio windows (2-9 floors): the work is done 100%.

Installation of apartment doors: work completed.

Interior decoration: work completed.

Facade: 100% completed.

Yard facade: 100% completed.

Landscaping: 96% completed.


Section 6:

Facade: 97% completed. Installation of facade protections continues.

Yard facade: work completed.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Roof: Completed.

Ties: Work complete.

Installation of patio windows (2-9 floors): the work is done 100%.

Window installation: 100% completed.

Installation of apartment doors: work completed.

Interior decoration: work completed.

Landscaping: 96% completed.


Parking:

Work is underway to install the floor at -1 level (readiness - 85%). Interior finishing works (65%) and laying of a terrace board (50%) are carried out. The main set of landscaping works is completed by 65%.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 60%

Accomplishment

Facade

Section 1
Windows - 100%
Facade - 100%
Section 2
Windows - 100%
Facade - 100%
Section 3
Windows - 100%
Facade - 100%
Section 4
Windows - 100%
Facade - 100%
Section 5
Windows - 100%
Facade - 100%
Section 6
Windows - 100%
Facade - 100%

Communications

Section 1
Inside - 100%
Outside - 100%
Section 2
Inside - 100%
Outside - 100%
Section 3
Inside - 100%
Outside - 100%
Section 4
Inside - 100%
Outside - 100%
Section 5
Inside - 100%
Outside - 100%
Section 6
Inside - 100%
Outside - 100%
Parking
Inside - 70%
Outside - 100%

Building 5

The grille of section № 1 is filled in. In section № 3 installation of vertical elements of the 2nd floor is carried out. Installation of the floor slab of the 6th floor in section № 4 has been completed. Installation of the facade exhibitor. In section № 6, the slab is poured on the 10th floor, and masonry works are carried out on the 9th floor.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 45%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 30%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 30%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 98%
Interior fittings - 0%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 99%
Facade - 90%
Section 2
Windows - 99%
Facade - 80%
Section 3
Windows - 99%
Facade - 60%
Section 4
Windows - 30%
Facade - 0%

Communications

Section 1
Inside - 80%
Outside - 100%
Section 2
Inside - 80%
Outside - 100%
Section 3
Inside - 60%
Outside - 100%
Section 4
Inside - 0%
Outside - 100%
Parking
Outside - 100%

Building 7

Installation of a sheet pile fence of a pit is carried out.

General construction works

Section 1
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Parking
Works against 0,000 - 0%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Facade - 0%
Section 2
Windows - 0%
Facade - 0%
Section 3
Windows - 0%
Facade - 0%
Section 4
Windows - 0%
Facade - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Parking
Outside - 0%

Building 9

Section 1

Facade: 100% completed.

Yard facade: 100% completed.

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Installation of windows (2-9 floors): work completed.

Installation of patio windows (2-9 floors): work completed.

Ties: Work complete.

Installation of apartment doors: the work is done 100%.

Interior decoration: work completed.

Roof: Completed.

Landscaping: 85% completed.


Section 2:

Facade: 95% completed.

Yard facade: 100% work done.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Ties: 100% complete.

Installation of windows: all work is completed.

Installation of apartment doors: the work is 100% completed.

Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.

Landscaping: 50% completed.


Section 3:

Facade: 100% completed.

Yard facade: 100% completed.

Internal networks (electricity, drainage and sewerage, heating and ventilation): work completed.

Ties: Work complete.

Installation of windows (2-9 floors): work completed.

Installation of patio windows (2-9 floors): work completed.

Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.

Installation of apartment doors: the work is done 100%.


Section 4:

Facade: 94% completed.

Yard facade: work completed.

Installation of patio windows (2-9 floors): installation is completed.

Installation of windows (2-9 floors): installation is complete.

Ties: Work complete.

Interior decoration: plaster work is 100% completed, the finishing layer is finished and the tiles are laid on the floor in public places.

Installation of apartment doors: the work is done 100%.

Landscaping: 90% completed.


Section 5:

Facade: 100% completed.

Yard facade: 100% completed.

Installation of windows (2-9 floors): installation is complete.

Installation of patio windows (2-9 floors): installation is complete.

Checkboxes: Complete.

Roof: Completed.

Installation of apartment doors: 100% completed.

Interior decoration: plastering, finishing and tiling on public floors have been completed.

Internal networks (drainage and sewerage, heating and ventilation): work completed.


Section 6:

Facade: 100% completed.

Yard facade: 100% completed.

Installation of windows (2-9 floors): installation is complete.

Installation of patio windows (2-9 floors): installation is complete.

Ties: 100% complete.

Internal networks (drainage and sewerage, heating and ventilation): work completed.

Installation of apartment doors: the work is done 100%.

Interior decoration: plastering, finishing and tiling on public floors have been completed.

Roof: Completed.


Parking:

The main set of landscaping works is completed by 95%. Work on the installation of the floor at 1 level (90%) and -1 level (45%) continues. Finishing works are performed at 1 level (65%) and -1 level (20%). Apply markup.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 2
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100100%
Interior fittings - 100%
Section 3
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 4
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 5
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Section 6
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 100%
Parking
Works against 0,000 - 100%
Frame - 100%
Brickwork - 100%
Interior fittings - 96%

Accomplishment

Facade

Section 1
Windows - 100%
Inside - 100%
Section 2
Windows - 100%
Inside - 95%
Section 3
Windows - 100%
Inside - 100%
Section 4
Windows - 100%
Inside - 95%
Section 5
Windows - 100%
Inside - 100%
Section 6
Windows - 100%
Inside - 100%

Communications

Section 1
Inside - 100%
Outside - 97%
Section 2
Inside - 100%
Outside - 97%
Section 3
Inside - 96%
Outside - 100%
Section 4
Inside - 1006%
Outside - 97%
Section 5
Inside - 100%
Outside - 100%
Section 6
Inside - 100%
Outside - 100%
Parking
Inside - 95%

Building 11

The grille of section № 1 is filled in. In section № 3 installation of vertical elements of the 2nd floor is carried out. Installation of the floor slab of the 6th floor in sections № 4 and 10th floor in sections №5 and №6 has been completed.

General construction works

Section 1
Works against 0,000 - 100%
Frame - 0%
Brickwork - 0%
Interior fittings - 0%
Section 2
Works against 0,000 - 100%
Frame - 1%
Brickwork - 0%
Interior fittings - 0%
Section 3
Works against 0,000 - 100%
Frame - 22%
Brickwork - 0%
Interior fittings - 0%
Section 4
Works against 0,000 - 100%
Frame - 50%
Brickwork - 0%
Interior fittings - 0%
Section 5
Works against 0,000 - 100%
Frame - 93%
Brickwork - 15%
Interior fittings - 0%
Section 6
Works against 0,000 - 100%
Frame - 90%
Brickwork - 15%
Interior fittings - 0%
Section 7
Works against 0,000 - 100%
Frame - 85%
Brickwork - 15%
Interior fittings - 0%
Section 8
Works against 0,000 - 100%
Frame - 40%
Brickwork - 0%
Interior fittings - 0%
Parking
Works against 0,000 - 100%
Frame - 50%
Brickwork - 0%
Interior fittings - 0%

Accomplishment

Facade

Section 1
Windows - 0%
Inside - 0%
Section 2
Windows - 0%
Inside - 0%
Section 3
Windows - 0%
Inside - 0%
Section 4
Windows - 0%
Inside - 0%
Section 5
Windows - 0%
Inside - 0%
Section 6
Windows - 0%
Inside - 0%
Section 7
Windows - 0%
Inside - 0%
Section 8
Windows - 0%
Inside - 0%

Communications

Section 1
Inside - 0%
Outside - 0%
Section 2
Inside - 0%
Outside - 0%
Section 3
Inside - 0%
Outside - 0%
Section 4
Inside - 0%
Outside - 0%
Section 5
Inside - 0%
Outside - 0%
Section 6
Inside - 0%
Outside - 0%
Section 7
Inside - 0%
Outside - 0%
Section 8
Inside - 0%
Outside - 0%

Progress of construction

12 January 2021

30 December 2020

23 December 2020

16 December 2020

10 December 2020

03 December 2020

27 October 2020

20 October 2020

11 October 2020

10 October 2020

03 October 2020

27 October 2020

15 October 2020

07 October 2020

01 October 2020

23 September 2020

16 September 2020

10 September 2020

03 September 2020

27 August 2020

19 August 2020

14 August 2020

03 August 2020

23 July 2020

14 July 2020

03 July 2020

25 June 2020

17 June 2020

11 June 2020

03 June 2020

27 May 2020

21 May 2020

12 May 2020

06 May 2020

28 April 2020

21 April 2020

14 April 2020

06 April 2020

30 March 2020

25 March 2020

16 March 2020

10 March 2020

05 March 2020

20 February 2020

10 February 2020

03 February 2020

27 January 2020

17 January 2020

11 January 2020

08 January 2020

21 December 2019

09 December 2019

09 December 2019

29 November 2019

22 November 2019

18 November 2019

11 November 2019

28 October 2019

21 October 2019

15 October 2019

07 October 2019

30 September 2019

17 September 2019

12 September 2019

02 September 2019

27 August 2019

19 August 2019

12 August 2019

02 August 2019

26 July 2019

22 July 2019

15 July 2019

05 July 2019

27 June 2019

24 June 2019

14 June 2019

07 June 2019

29 May 2019

23 May 2019

17 May 2019

10 May 2019

04 May 2019

26 April 2019

19 April 2019

22 March 2019

13 March 2019

07 March 2019

27 февраля 2019

21 February 2019

14 February 2019

07 February 2019

04 February 2019

21 January 2019

11 January 2019

08 January 2019

28 December 2018

18 December 2018

20 November 2018

09 November 2018

02 November 2018

26 October 2018

19 October 2018

08 October 2018

26 September 2018

02 October 2018

26 September 2018

18 September 2018

12 September 2018

03 September 2018

27 August 2018

20 August 2018

16 August 2018

7 August 2018

30 July 2018

23 July 2018

16 July 2018

9 July 2018

2 July 2018

23 June 2018

18 June 2018

12 June 2018

May 29, 2018

May 22, 2018

May 15, 2018

May 2, 2018

April 16, 2018

April 10, 2018

March 28, 2018

March 19, 2018

March 5, 2018

February 28, 2018

February 21, 2018

February 13, 2018

February 8, 2018

January 24, 2018

January 15, 2018

January 09, 2018

December 26, 2017

December 20, 2017

December 12, 2017

November 30, 2017

November 28, 2017

November 21, 2017

November 11, 2017

November 02, 2017

October 25, 2017

October 11, 2017

October 05, 2017

September 22, 2017

September 18, 2017

September 11, 2017

September 4, 2017

August 22, 2017

August 10, 2017

June 16, 2017

June 12, 2017

June 2, 2017

May 23, 2017

May 12, 2017

March 31, 2017

February 20, 2017

February 9, 2017

January 30, 2017

January 14, 2017

December 20, 2016

December 8, 2016

November 14, 2016